| Name: |
Kharyaga Petrochemical complex,
Stage 2 |
| Location: |
Kharyaga fields, Republic of
Komi |
| Client: |
TOTAL FINA ELF |
| General Contractor: |
PETROFAC International Ltd |
| HVAC Contractor: |
AIRCO Engineering & Trading
Ltd |
|
|
| |
| |
Heating, Ventilation and Air Conditioning
(fresh air ducting system) of a petrochemical
plant consisting of 11 Buildings. Total area covered
of 3,736 sq. meters. |
|

| |
| |
Buildings classified as follows: |
| |
5 Buildings belong to hazardous
area (zone 2), 1 building belongs to safe area
and 4 Buildings belong to non-hazardous area. |
|

| |
| |
Extremely short closedown time.
All HVAC equipment is ex-proof. Ex-proof Heating
Batteries up to 870 kW. Stand-by Unit with automatic
switch. |
|

| |
| |
Heating media: oil
at 260 cDeg. |
|

| |
- HVAC Mechanical and Control Systems engineering
and designing. The process is from Preliminary
Drawings to As-built Drawings including all
the calculation work.
- HVAC material and equipment selection and
supply including customs clearance assistance.
- HVAC IOM Documents compiling.
- HVAC SAT Procedures compiling.
- HVAC Commissioning supervision.
|
|
|
|